Title:
|
Erlang distributed activity times in stochastic activity networks (English) |
Author:
|
Abdelkader, Yousry H. |
Language:
|
English |
Journal:
|
Kybernetika |
ISSN:
|
0023-5954 |
Volume:
|
39 |
Issue:
|
3 |
Year:
|
2003 |
Pages:
|
[347]-358 |
Summary lang:
|
English |
. |
Category:
|
math |
. |
Summary:
|
It is assumed that activity times in stochastic activity networks (SANs) are independent Erlang random variable (r.v.). A recurrence method of determining the $k$th moments of the completion time is presented. Applications are provided for illustration and are used to evaluate the applicability and appropriateness of the Erlang model to represent activity network. (English) |
Keyword:
|
project planning |
Keyword:
|
PERT |
Keyword:
|
Erlang distribution |
MSC:
|
33B99 |
MSC:
|
60E05 |
MSC:
|
90B15 |
MSC:
|
90B35 |
MSC:
|
90C35 |
MSC:
|
90C39 |
idZBL:
|
Zbl 1249.90305 |
idMR:
|
MR1995739 |
. |
Date available:
|
2009-09-24T19:54:40Z |
Last updated:
|
2015-03-23 |
Stable URL:
|
http://hdl.handle.net/10338.dmlcz/135537 |
. |
Reference:
|
[1] Bendell A., Solomon, D., Carter J. M.: Evaluating project completion times when activity times are Erlang distributed.J. Opl. Res. Soc. 46 (1995), 867–882 10.1057/jors.1995.118 |
Reference:
|
[2] Devroye L. P.: Inequalities for the completion times of stochastic PERT networks.Math. Oper. Res. 4 (1979), 441–447 Zbl 0427.90053, MR 0549130, 10.1287/moor.4.4.441 |
Reference:
|
[3] Elmaghraby S. E.: On the expected duration of PERT type networks.Management Sci. 13 (1967), 299–306 Zbl 0158.38303, 10.1287/mnsc.13.5.299 |
Reference:
|
[4] Elmaghraby S. E.: The estimation of some network parameters in PERT model of activity network: review and critique.In: Advances in Project Scheduling, Chapter I, Part III (R. Slowinski and J. Weglarz, eds.), Elsevier, Amsterdam 1989, pp. 371–432 MR 1060141 |
Reference:
|
[5] Elmaghraby S. E.: On criticality and sensitivity in activity networks.European J. Oper. Res. 127 (2000), 220–238 Zbl 0990.90119, 10.1016/S0377-2217(99)00483-X |
Reference:
|
[6] Fulkerson D. R.: Expected critical path lengths in PERT networks.Oper. Res. 10 (1962), 808–817 Zbl 0124.36304, 10.1287/opre.10.6.808 |
Reference:
|
[7] Kamburowski J.: Normally distributed activity durations in PERT networks.J. Opl. Res. Soc. 36 (1985), 1051–1057 Zbl 0579.90052, 10.1057/jors.1985.184 |
Reference:
|
[8] Kamburowski J.: An upper bound on the expected completion time of PERT networks.European J. Oper. Res. 21 (1985), 2, 206–212 Zbl 0569.90047, MR 0811084, 10.1016/0377-2217(85)90032-3 |
Reference:
|
[9] Kleinrock L.: In: Queuing Systems, Volume I.Wiley, New York 1975 |
Reference:
|
[10] Kulkarni V. G., Adlakha V. G.: Markov and Markov regenerative PERT networks.Oper. Res. 34 (1986), 5, 769–781 Zbl 0615.90042, MR 0884303, 10.1287/opre.34.5.769 |
Reference:
|
[11] Loulou R., Beale T.: A comparison of variance reducing techniques in PERT simulations.INFOR Canadian J. Opl. Res. 14 (1976), 259–269 Zbl 0354.62027 |
Reference:
|
[12] Magott J., Skudlarski K.: Estimating the mean completion time of PERT networks with exponentially distributed duration of activities.European J. Oper. Res. 71 (1993), 70–79 10.1016/0377-2217(93)90261-K |
Reference:
|
[13] Robillard P.: Expected completion time in PERT networks.Oper. Res. 24 (1976), 177–182 Zbl 0324.90025, MR 0406447, 10.1287/opre.24.1.177 |
Reference:
|
[14] Ross S. M.: Stochastic Process.Wiley, New York 1983 |
Reference:
|
[15] Sculli D.: The completion time of PERT networks.J. Opl. Res. Soc. 34 (1983), 155–158 Zbl 0502.90045, 10.1057/jors.1983.27 |
Reference:
|
[16] Tavares L. V.: A review of the contribution of operational research to project management.European J. Oper. Res. 136 (2002), 1–18 Zbl 1086.90532, 10.1016/S0377-2217(01)00097-2 |
. |